Title | Due date | Budget | Progress | ||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Requirements specified
All requirements are known
There are a few details not covered in the existing spec, namely template specifications. We also identified that we need to have a clear terminology. |
|
|
|||||||||||||||||||||||||
Initial Technology decided
Main technologies decided
|
|
|
|||||||||||||||||||||||||
Media player pages available
The media player pages are working.
No framework yet |
|
|
|||||||||||||||||||||||||
Release to ACT
Steve hand's over to ACT
|
Sep 15, 2008 |
|
|
||||||||||||||||||||||||
Ready for Beta CDs
Ready to put on CDs
|
Sep 22, 2008 |
|
|
||||||||||||||||||||||||
Public release
Get it out there
25th in Sheffield and 29th Sept. in Doncaster. Went well |
Sep 25, 2008 |
|
|
||||||||||||||||||||||||
Project Website available on ACT site
The project web site up and running so that users and developers can find out about, get and contribute.
|
Sep 30, 2008 |
|
|
||||||||||||||||||||||||
0.1.1 Release
Release to go with announcement to dev community and others
|
Oct 10, 2008 |
|
|
||||||||||||||||||||||||
Nov 19, 2008 |
|
|
|||||||||||||||||||||||||
0.1.2 Release
Critical fixes that we ran out of time for in 0.1.0
|
Aug 14, 2009 |
|
|
||||||||||||||||||||||||
Release 0.5 RC1 Mavis@School for local testing
Code completed ready for testing.
Given to Simon and Peter.
|
Aug 17, 2009 |
|
|
||||||||||||||||||||||||
Release 0.1.6 Mavis@School for research local testing
Tested locally on various PCs or networks
Given to researcher |
Sep 21, 2009 |
|
|
||||||||||||||||||||||||
Release 0.5 - Mavis@School ready to install in schools
Required features coded and ready to be handed over to schools for installation and testing.
3 schools will have Maavis installed and used with researchers studying use by switch users Heatherwood, Doncaster - standalone installations , Maavis login Sevenhills, Sheffield - networked, many existing programs Greenacres, Barnsley - networked |
Sep 25, 2009 |
|
|
||||||||||||||||||||||||
Release 1.0.0 (Maavis@school complete)
Maavis@school Ready to be used in schools
|
Jan 31, 2010 |
|
|
||||||||||||||||||||||||
BAES training day
Ready for staff training day for BAES KT on 27 July. Need to get to them by 23.
|
Jul 23, 2010 |
|
|
||||||||||||||||||||||||
BAES update
Changes for BAES resulting from training day meeting
|
Sep 15, 2010 |
|
|