Show due date of dependent tasks
I guess this bug is something open for discussion instead of a direct fix.
To understand the bug, please follow this process:
1) Create action A without a due date
2) Create action B with due date tomorrow
3) Make B depend on A
Assuming that action B really hsa a deadline of tomorrow and A needs to be done before B, it follows that A also has a deadline of tomorrow. This currently is not shown (although it is shown that A has at least one depending action).
I'd love to see the first of the dependent actions' deadlines shown for some action so that its urgency is clearly visible.
To understand the bug, please follow this process:
1) Create action A without a due date
2) Create action B with due date tomorrow
3) Make B depend on A
Assuming that action B really hsa a deadline of tomorrow and A needs to be done before B, it follows that A also has a deadline of tomorrow. This currently is not shown (although it is shown that A has at least one depending action).
I'd love to see the first of the dependent actions' deadlines shown for some action so that its urgency is clearly visible.
Leave a comment