This space is used for the project named ODS - Online Delivery System

The project's purpose is to create the Online Vehicle Tracking and Order Dispatching System

The information of the team in charge of this project:

1. Team leader: 1. Denny Cahyadi (softix2) - in charge of coding part

2. Ritesh Kalra (softix1) - in charge of webpage design and user interface

3. Jefry HardyHardy (softix4) - - in charge of coding part

4. Andri Soenoyo (softix6) - - in charge of the online database

5. Ho Hoang Hung (softix3) - in charge of the online database

6. Pham Nguyen Nguyen (softix5) - in charge of webpage design and user interface

The schedule for each step of the project

19 August - 29 Aug 2008: Finish the SRS, use-case diagram and use-case description

30 Aug - 12 September 2008: Finish the class (object), collaboration and sequence diagrams

13 Sep - 26 Sep 2008 (including the recess week): Refine the class (object), collaboration and sequence diagrams and start to build the website

27 Sep - 17 October 2008: Code and compile, testing (black box and white box)

18 Oct - Oct 20 (before lab 5): finish the sub-system to run demo

1 week after exam: finish the project